[dts] [PATCH V3 0/5] update test plan to sync with testcase
lingwei
weix.ling at intel.com
Mon Sep 7 18:49:24 CEST 2020
update test plan to sync with testcase and fix wrong describle
lingwei (5):
test_plans/nic_single_core_perf_test_plan:update test plan to sync
with testcase
test_plans/pmd_test_plan:update test plan to sync with testcase
test_plans/ptpclient_test_plan:update test plan to sync with testcase
test_plans/vf_l3fwd_test_plan:update test plan to sync with testcase
test_plans/vmdq_test_plan:update test plan to sync with testcase
test_plans/nic_single_core_perf_test_plan.rst | 7 +++++++
test_plans/pmd_test_plan.rst | 7 +++++++
test_plans/ptpclient_test_plan.rst | 3 +++
test_plans/vf_l3fwd_test_plan.rst | 9 +++++++++
test_plans/vmdq_test_plan.rst | 5 ++++-
5 files changed, 30 insertions(+), 1 deletion(-)
--
2.17.1
More information about the dts
mailing list