[dts] [PATCH V3 0/5] update test plan to sync with testcase

lingwei weix.ling at intel.com
Mon Sep 7 18:49:24 CEST 2020


update test plan to sync with testcase and fix wrong describle

lingwei (5):
  test_plans/nic_single_core_perf_test_plan:update test plan to sync
    with testcase
  test_plans/pmd_test_plan:update test plan to sync with testcase
  test_plans/ptpclient_test_plan:update test plan to sync with testcase
  test_plans/vf_l3fwd_test_plan:update test plan to sync with testcase
  test_plans/vmdq_test_plan:update test plan to sync with testcase

 test_plans/nic_single_core_perf_test_plan.rst | 7 +++++++
 test_plans/pmd_test_plan.rst                  | 7 +++++++
 test_plans/ptpclient_test_plan.rst            | 3 +++
 test_plans/vf_l3fwd_test_plan.rst             | 9 +++++++++
 test_plans/vmdq_test_plan.rst                 | 5 ++++-
 5 files changed, 30 insertions(+), 1 deletion(-)

-- 
2.17.1